Number Proposed Dwellings

2 Luxury Townhouses

Estimated Project Time Frame

9 months

Project Updates

Project Update From 20 Rusden Pty Ltd as at 5th February, 2019


  • Developer Update with photos
  • Preliminary Civil Engineering design complete
  • Financier Quantity Survey costing report underway
  • IDAS forms for building permits to be completed this week
  • Road closure permits lodged
  • Plumbing and Drainage BCC lodged paid for and approved
  • Mains Power Energex application Submitted
  • Subcontract Pricing progressing
  • Detailed Structural Engineering Design commenced and should be complete Friday
  • Boundary Identification Survey to be commenced this week
  • Preliminary Plumbing Design Complete
  • Building Approval Drawings almost complete and fee agreement signed with building certifier
  • Preliminary Mechanical ventilation and Air-conditioning design complete
  • New video and photos uploaded of boundary fence removal


Project Update From 20 Rusden Pty Ltd as at 7th December, 2018

  • DA Approval granted 5/12/18
  • Floors have been replaced on level 1 and 2 on one half of the building
  • Edge protection has been installed on the roof to start stripping the terracotta roof
  • New roof will be installed next week
  • Excavation to the front of the property is scheduled to commence in the next week

Next update February 2019 due to Holiday Season

Project Update From 20 Rusden Pty Ltd as at 5th November, 2018

  • Demolition continuing
  • Installation of structural beams & commencement of framing top floor
  • Electrical, plumbing and drainage are all due to start this month
  • DA Approval expected towards the end of November
  • New video and photos uploaded

Project Update From 20 Rusden Pty Ltd as at 5th October, 2018

  • Hydraulic, electrical and civil engineers are now commencing work on the design and documentation, along with the required applications
  • Interior demolition work in progress
  • DA Approval expected within 4 weeks
  • New video and photos uploaded

Project Update From 20 Rusden Pty Ltd as at 5th September, 2018

  • DA lodged with council
  • Photo's and video added to this update

View Rusden St DA

Project Update From 20 Rusden Pty Ltd as at 8th August, 2018

  • Property settled 3rd August, 2018
  • Internal demolition commenced

Project Videos

Project Video Update 05.09.18
Project Video Update 05.10.18

Send us an email

Send us an email

We Find Houses
4/57 Township Drive
Burleigh Heads, Queensland 4220
Australia
Postal:
PO Box 105
West Burleigh, Queensland 4219
Australia
Phone: 1800 600 890
Business Hours: 9am – 5pm, Monday – Friday